Yolanda Rehab & Shelter / Livelihood Project with Gawad Kalinga
Updates on the Gawad Kalinga projects in Cadiz City, Negros Occidental and Batad, Iloilo.

Cadiz City, Negros Occidental
Livelihood. Please note that the livelihood projects will take time before we can implement. The homes and community organizing of the families are priority before the livelihood programs.

Batad, Iloilo
Layout and excavation just started this week. Reason for delay: Waited for the LGU to start grading but until now there’s no action from the LGU. Our team decided to go ahead and start the layout as based on their assessment, there’s no need to wait for the grading to be done as land is leveled anyway. We will still try our best to completed the project end of June.

Target completion date: End of June 2015.


From Balita Issue 3600
See this story as printedRead the whole issue